This question has been flagged
2 Replies
3755 Views

I would like to run the mrp procurement planner manually v7

Avatar
Discard
Best Answer

Go to menu "Warehouse / Scheduler / Run Schedulers"

Note: Make sure you have the option "technical features" activated for your user in Settings > Users.

Avatar
Discard
Author

For V7 ???

Yes, this is for v7.

Author

found it. thanks a lot!!

Best Answer

Is this applicable to MRP scheduler as well? I have tried it but no affect.

Avatar
Discard